Shelly
 Clarizen Fan Posts:21

 |
| 10 Dec 2009 10:40 AM |
|
Does the work week, work hours a day, and days per month that is set up in the organization settings affect the scheduling of the projects?
Thanks |
|
|
|
|
Josh Santos
 Clarizen Veteran Posts:391

 |
| 10 Dec 2009 11:00 AM |
|
Absolutely. For example, if your work week is from Monday to Thursday, no work will be scheduled by default on Friday, Saturday, or Sunday. Work hours per day has a similar effect. If your work day is 6 hours and you schedule a 9 hour task, then that task will take up all of 1 day and half of a second day. Days per month primarily has an effect if you as scheduling things in month increments (entering 1mo, 2mo in duration). |
|
|
|
|
Josh Santos
 Clarizen Veteran Posts:391

 |
| 10 Dec 2009 11:17 AM |
|
One more thing that I forgot to mention. For the duration in your schedule, you can also set consecutive days that will ignore non-working days like weekends and holidays. All you do is add a "c" before the time unit. So if you want to create a task that spans 6 days including weekends and holidays, you can schedule it for 6cd (instead of 6d). 12 consecutive hours would be 12ch, and 5 consecutive weeks would be 5cw. |
|
|
|
|
Shelly
 Clarizen Fan Posts:21

 |
| 10 Dec 2009 12:07 PM |
|
I see now, thank you so much for that information. |
|
|
|
|
unicorn
 Clarizen Pro Posts:171

 |
| 14 Dec 2009 01:04 AM |
|
the abilty do define a work schedule that is inconsistent would catter to our organization, I have not mentioned this before but as a fact we work Sun- Wen 7:15 am - 5 pm and thur 7:15 am - 3pm - appropriate for the location and the production. I would like to be able to plan as per this definition - I wonder if this can be accomidated in Clarizen. |
|
|
|
|
Josh Santos
 Clarizen Veteran Posts:391

 |
| 14 Dec 2009 06:18 PM |
|
We'll be able to accommodate this in the future with personal calendars. |
|
|
|
|
unicorn
 Clarizen Pro Posts:171

 |
| 15 Dec 2009 06:18 AM |
|
Is this in the next 2 releases? |
|
|
|
|
Josh Santos
 Clarizen Veteran Posts:391

 |
| 15 Dec 2009 10:35 AM |
|
I'm keeping my fingers crossed for the release after 4.3 but it is not set in stone and could easily be a release after. We have some big development plans for 2010 and it could push certain features back. |
|
|
|
|